Concrete Keyway: What It Does, Where It Goes and How to Form One

By Mohamed Skhiri · Updated November 2026 · 15 min read
Rebar and concrete keyway forms set along wall bases before a concrete pour

Photo: MTA Capital Construction, Wikimedia Commons, CC BY 2.0

Quick Answer

A concrete keyway is a groove formed in one concrete pour so that the next pour fills it and locks the two together, like a tongue in a groove. The most common is the footing keyway: a beveled 2x4 pressed into the top of a fresh footing and pulled out after the concrete sets, leaving a groove that the foundation wall fills. Keyways also appear in keyed construction joints in slabs, walls and pavements, and as shear keys between precast pieces. A keyway helps resist sliding and lengthens the path water must take through a joint, but in modern practice rebar dowels carry most of the load, and keyed joints are discouraged in slabs that carry heavy wheel traffic. Forming a keyway costs very little: a few dollars of lumber per foot, or about $2 to $6 per linear foot for metal key joint forms.

Wherever concrete is placed in more than one pour, there is a joint, and a joint is a weak spot. The two pours do not bond like one continuous piece, so loads and water look for a way through. For more than a century, builders have used a simple trick to strengthen these joints: shape the edge of the first pour so the second one interlocks with it. That interlocking shape is the concrete keyway. The photo above shows keyway forms and reinforcing steel set along the base of retaining walls on a large rail project, ready for the next concrete placement.

This guide explains what a concrete keyway does, how to form footing keyways and keyed joints, where keyways help and where dowels work better, how keyways are used with waterstops and in precast and bridge construction, typical sizes, mistakes to avoid and what keyways cost.

What Does a Concrete Keyway Do?

Section diagram of a footing concrete keyway and a keyed slab construction joint

As the diagram shows, a concrete keyway turns a flat joint into an interlocking one. It does three main jobs.

It resists sliding (shear). A foundation wall sitting on a flat footing is held in place only by friction, by its weight and by any steel crossing the joint. When soil pushes sideways on a basement or retaining wall, the base of the wall wants to slide across the footing. The concrete key in the concrete keyway gives the wall a lip to bear against, adding shear resistance at the joint.

It keeps the two sides aligned. In slabs and pavements, a keyed joint ties the edges of adjacent pours together vertically, so one side cannot rise or drop relative to the other, at least under light loads.

It slows water. A straight, flat cold joint gives water a short path from outside to inside. A concrete keyway forces water to travel up, across and down around the key, which lengthens the path and slows leaks. In basements and water tanks, a waterstop is often placed in or beside the keyway for a much better seal.

A concrete keyway is not a substitute for reinforcement. Building codes and engineers rely mainly on dowels or continuous rebar crossing the joint to carry loads; the keyway helps, but on its own it can crack and spall if overloaded. See cold joints in concrete and rebar in concrete.

Footing Keyways

The footing keyway is the most familiar concrete keyway for builders and homeowners. Continuous footings for houses, garages and retaining walls are usually poured first, and the foundation wall, whether poured concrete or concrete block, is built on top days or weeks later. A keyway formed in the top of the footing creates a groove that the wall concrete fills, locking wall and footing together.

How to form a footing keyway. The traditional method uses a 2x4 or 2x6 with both long edges beveled, so the board tapers and can be pulled out of the hardened concrete without breaking the edges of the groove. After the footing concrete is placed, screeded and has firmed up slightly, the beveled board is pressed into the top of the footing along the center of where the wall will sit, flush with or slightly below the surface, and held in place with stakes or spreader boards resting on the forms. Oil or a form release agent on the board makes removal easier. Once the concrete has set enough to hold its shape, often the next morning, the board is pried out, leaving a clean, tapered concrete keyway.

Footing keyway size. A 2x4 gives a groove about 1.5 inches deep and 3.5 inches wide, a common size for residential foundation walls 8 to 10 inches thick. Thicker walls and retaining walls often use a 2x6 or a larger key specified by the engineer. The keyway should be centered under the wall so there is solid concrete on both sides of the groove.

Keyway plus dowels. In most modern foundations, vertical rebar dowels are set in the footing at regular spacing so they stick up into the wall. The dowels and the concrete keyway work together: the dowels carry tension and most of the shear, while the concrete keyway adds shear resistance and a longer water path. Many building departments and engineers accept either a keyway or dowels for basic residential walls, but retaining walls and walls holding back significant soil almost always require dowels. Check the plans and local code. See concrete footings and concrete footing cost.

Block walls. When a concrete block wall sits on the footing, the first course is set in mortar, and the keyway is less useful because the block cores and mortar do not fill the groove fully. Vertical dowels grouted into the block cores are the usual connection instead. Some builders still form a shallow keyway to help the mortar bed grip and to resist sliding.

Step by Step: Forming a Footing Keyway

1. Make the key form. Rip both long edges of a straight 2x4 at about a 15 to 20 degree bevel so the bottom face is narrower than the top. Make enough lengths to run the full footing, and coat them with form oil or a release agent so the concrete keyway releases cleanly.

2. Mark the wall line. Snap or string the centerline of the future wall on the footing forms so the concrete keyway ends up centered under the wall, not under one face of it.

3. Place and screed the footing. Pour, consolidate and strike off the footing concrete to the correct height, and set any vertical dowels the plans require, checking that they will not fall inside the groove.

4. Set the key. Once the surface has firmed slightly, press the beveled board into the concrete along the line, wide face up, until its top is flush with the footing surface. Tap it down with a hammer and block, and hold it in place with stakes or cleats nailed to boards spanning the forms so it cannot float.

5. Finish around it. Float the concrete next to the board so the edges of the concrete keyway are tight and level.

6. Strip the key. After the concrete has set enough to hold its shape, usually within a day, pry the board out gently, working along its length. Clean the groove and keep the footing moist while it cures. Before the wall is placed, clear the keyway again of any debris, mud or water.

Keyed Construction Joints in Slabs

When a large slab cannot be placed in one day, the edge of each day's pour forms a construction joint. A keyed construction joint uses a concrete keyway form, usually a wood strip or a galvanized steel key form fastened to the bulkhead, so the first pour has a groove along its edge. The next pour fills the groove, forming a tongue. The concrete keyway keeps the two slab edges at the same height.

Keyed joints were once very common in floor slabs and pavements. Experience showed problems, though. In slabs carrying forklifts, trucks or other heavy wheel loads, the narrow concrete above or below the key, especially on the female side, tends to crack and break off as the joint opens with shrinkage and wheels pound across it. Guidance from the American Concrete Institute on slab construction now generally discourages keyed joints for slabs that carry heavy traffic and recommends smooth dowels or plate dowels instead, which transfer load across the joint while letting it open and close.

Keyed joints still have a place in lighter-duty work: residential slabs, sidewalks, patios and some light commercial floors, where loads are modest and the main goal is to keep adjacent pours aligned. Even there, the key should be sized to the slab thickness, and slabs thinner than about 5 or 6 inches are usually too thin for a strong concrete keyway. See control joints in concrete and concrete expansion joints.

Keyways in Pavements and Precast Panels

Transverse concrete keyway joint between precast concrete pavement panels with dowel slots

Photo: Federal Highway Administration, Wikimedia Commons, public domain (cropped)

Precast concrete pavement systems use concrete keyways and dowels together. The panels in the photo above are cast in a plant with a concrete keyway along the transverse joint and slots for dowel bars, then set in place on a highway and grouted. The keyway helps align panels as they are lowered and gives the grout something to lock into, while the dowels carry the wheel loads from one panel to the next. Similar keyed and doweled joints are used in precast retaining wall panels, tilt-up panels and box culverts. See dowel bars in concrete pavement and precast concrete.

Shear Keys in Bridges and Precast Beams

Concrete keyway shear key between adjacent precast bridge beams before grouting

Photo: Federal Highway Administration, Wikimedia Commons, public domain

On bridges built from side-by-side precast box beams or slab beams, each beam has a shaped edge, and adjacent beams form a long, narrow concrete keyway between them, called a shear key. The photo above shows the gap between two beams before it is filled. The key is filled with grout or concrete, often a high-performance or ultra-high-performance material, so that a heavy truck crossing one beam shares its load with the beams next to it. When shear keys crack, water and deicing salts reach the beams and the deck can start acting like separate planks, which is one of the most common maintenance problems on this kind of bridge. Modern designs use deeper keys, transverse post-tensioning and stronger grouts to prevent it.

Keyways and Waterstops

Basements, water tanks, pools, tunnels and other structures that must keep water in or out treat every construction joint as a potential leak. A concrete keyway alone lengthens the water path, but water can still find its way through cracks along the key. For a reliable seal, designers add a waterstop: a PVC or rubber strip cast half into each side of the joint, a hydrophilic strip that swells when wet, or a crystalline or injected system. Some waterstops are placed in the center of the concrete keyway; others sit beside it. In many modern tanks, engineers drop the keyway altogether and rely on a roughened joint surface, continuous reinforcement and a waterstop, because the keyway can make it harder to clean the joint and consolidate concrete around the waterstop. See is concrete waterproof.

Keyway Forms: Wood, Metal and Plastic

Beveled lumber. The cheapest concrete keyway form, made on site from 2x4 or 2x6 boards ripped to a taper. It is easy to make but must be oiled, set straight and removed carefully.

Metal key joint forms. Galvanized steel forms that combine a keyway shape with a stake or bulkhead, often with knockouts for dowels. They give a consistent profile and can be left in place as part of the joint in some slab work.

Plastic keyway strips. Reusable plastic profiles that attach to formwork for walls and slabs. They are light, release easily and produce a clean concrete keyway.

Rubber and foam inserts. Used where a recess is needed for a joint sealant or waterstop rather than a structural key.

How to Prepare a Keyway Before the Next Pour

A concrete keyway only works if the second pour bonds to the first. Before the next placement:

Clean the joint. Remove the form, then clean out sawdust, mud, loose concrete, standing water and any curing compound from the keyway. A wire brush, compressed air or water jet works well.

Roughen if needed. Smooth surfaces bond poorly. Many specifications require a roughened joint surface, achieved by brushing or water-blasting the fresh concrete or by light chipping after it hardens.

Dampen. Wet the joint surface ahead of the pour so it is damp but without puddles, so the old concrete does not draw water out of the new concrete.

Consolidate carefully. Vibrate the new concrete so it fully fills the concrete keyway and flows around dowels and waterstops without voids. Do not drag concrete into the key with the vibrator; place it close by and vibrate it in. See concrete vibrator.

Choosing a Keyway for Concrete Footings, Walls and Slabs

Picking the right keyway for concrete work depends on what the joint has to do. For a house footing that will carry a poured or block foundation wall, a beveled 2x4 keyway for concrete footings is standard, combined with whatever dowels the plans require. For a thicker basement or retaining wall, the engineer may call for a 2x6 or wider key, or for a roughened joint and heavier dowels instead. For a slab construction joint under foot traffic or cars, a metal key form or a doweled joint both work; for warehouse floors with forklifts, a keyway for concrete slabs is the wrong choice and load-transfer dowels should be used. For water-retaining structures, choose the waterstop first and then decide whether a concrete keyway helps or simply makes the joint harder to clean. When in doubt, follow the drawings: the right keyway for concrete in any given joint is the one the designer specified, because it was chosen together with the reinforcement.

Keyways in Retaining Walls

Retaining walls use the concrete keyway idea in two places. The first is the familiar footing-to-wall keyway at the construction joint where the stem wall meets the footing. The second is a base shear key: a block of concrete cast downward from the bottom of the footing into the soil, running along the length of the wall. When soil behind the wall pushes it sideways, the base key bears against undisturbed soil in front of it, adding resistance to sliding beyond what friction under the footing provides. Base shear keys are designed by the engineer as part of the wall's stability calculations, with size and depth set by the soil type and wall height. On small landscape walls they are rare, but on cantilevered retaining walls several feet tall or more they are common. See concrete retaining wall.

Keyways vs. Dowels vs. Roughened Joints

Engineers have three main tools for joining two concrete pours, and they are often used together.

Concrete keyway. A shaped groove and tongue. Cheap and easy to form. Adds shear resistance and a longer water path, and keeps edges aligned. Weaknesses: the key can crack under heavy, repeated loads, and it does not hold the two pours together in tension.

Dowels and reinforcing steel. Steel bars crossing the joint. Deformed rebar dowels tie the pours together and carry tension and shear; smooth dowels in slabs transfer load while letting the joint open and close. Dowels are the main structural connection in almost all modern concrete work.

Roughened joint surface. Intentionally roughening the first pour, for example to an amplitude of about a quarter inch, creates interlock over the whole surface rather than at a single key. Building codes and design standards give roughened, clean joints with reinforcement crossing them a defined shear-friction strength, which is why many engineers prefer roughening plus dowels to a formed keyway.

In practice, a footing commonly has both a concrete keyway and dowels, a slab joint has dowels and sometimes a key, and a large wall or tank joint has roughening, reinforcement and a waterstop.

Keyways in Walls and Tilt-Up Panels

Tall cast-in-place walls are often poured in lifts or sections, with horizontal and vertical construction joints between them. A keyway for concrete walls at those joints is formed with a wood or plastic strip fastened inside the forms. Vertical keyways at the ends of wall sections help adjacent pours stay aligned and resist out-of-plane movement. In tilt-up and precast wall panels, edges are sometimes cast with a keyed or rebated profile so panels nest together and joint sealant sits in a protected recess. Where walls must be watertight, the same rules apply as for tanks: clean the concrete keyway, roughen it, and add a waterstop.

Repairing a Damaged Keyway or Joint

Keyways sometimes come out of the form broken or chipped, or a keyed slab joint spalls after years of traffic. For a footing keyway damaged during form removal, small chips can usually be left, since the wall concrete will fill them; large broken sections should be cleaned out so loose pieces do not create a weak plane under the wall. For spalled keyed joints in slabs, the usual repair is to saw cut along both sides of the damaged area, remove the broken concrete, clean and prime the surface, and fill with a repair mortar or epoxy mortar, then recut the joint so it can still move. If the joint keeps failing, adding dowels by retrofitting slots across it is a more lasting fix. See concrete repair cost and epoxy concrete crack repair.

Inspection Points for Keyways

Before a foundation wall pour, inspectors and site supervisors check that the concrete keyway is in the right location and continuous, that it is clean and free of standing water, that dowels are at the specified size, spacing and embedment, and that any waterstop is secured and undamaged. On slabs, they check that key forms or dowel baskets are straight, at the right height and perpendicular to the joint. Taking a photo of each joint before the next pour is cheap insurance: once the concrete is placed, a missing keyway or dowel is invisible and expensive to fix.

Common Mistakes with Concrete Keyways

Square-edged forms. A key form with straight, unbeveled sides is hard to remove and often breaks the edges of the groove. Always bevel or taper the form.

Setting the key too early or too late. Pushed in while the footing is very wet, the board can sink or float; pushed in too late, it will not seat. Set it after the concrete has been screeded and firmed slightly, then check the line.

Off-center keyways. A groove too close to one edge of the wall leaves a thin, weak lip of concrete that can break off.

Relying on the concrete keyway alone. Where the plans call for dowels, a concrete keyway is not a substitute.

Using keyed joints under heavy traffic. In warehouse and industrial floors, use dowels designed for the load instead of a keyed joint.

Dirty joints. Debris and laitance left in the concrete keyway create a weak plane that leaks and cracks.

Concrete Keyway Cost

Forming a concrete keyway adds very little to a concrete job. A beveled 2x4 key form costs only a few dollars per 8-foot length, and the boards can be reused several times. Metal key joint forms for slabs typically run about $2 to $6 per linear foot depending on height and features. Labor to set and strip a footing keyway on a typical house foundation is a small part of the footing crew's day. On commercial and civil projects, waterstops and dowel systems at keyed joints add more cost, often $5 to $20 or more per linear foot installed depending on type. Compared with repairing a leaking or shifting joint later, the cost of a well-formed concrete keyway with proper dowels is minor. See concrete block wall cost.

Frequently Asked Questions

What is a keyway in concrete?

A groove formed in one pour so the next pour fills it and interlocks, adding shear resistance and a longer water path at the joint.

Do footings need a keyway?

Many residential plans call for either a footing keyway or rebar dowels. Retaining walls and engineered walls usually require dowels; check your plans and local code.

How deep is a footing keyway?

A beveled 2x4 makes a concrete keyway about 1.5 inches deep and 3.5 inches wide, common for 8- to 10-inch walls.

Are keyed joints good for slabs?

For light-duty slabs they help keep edges aligned, but for slabs with heavy wheel traffic, dowels are recommended instead.

What is a shear key?

A grouted keyway between precast beams or panels that lets them share loads.